Postby pysergio » Wed Jul 11, 2012 7:03 am

Hello,

I've asked this question a week ago in related topic, but still no answer.
Please let me know if the attached signals are implemented in 9.1.9 or when they we'll be implemented?
How to cancel alternative activities if one of them is done?
Tnx in advance.

Best regards,
Sergyy.
pysergio
 
Posts: 3
Joined: Mon May 28, 2012 7:29 am

Re: Are the attached signals implemented in 9.1.9?

Postby BizAgi Xpress Support » Wed Jul 11, 2012 11:24 am

Dear Pysergio,
Thank you for your interest in Bizagi.

Concerning your question, indeed the attached signal events are not currently supported in the 9.1.9 version, and we have no current approximation (release or date) as to this feature’s release.

To cancel an activity, you may use a pattern in which the activity and an event are preceded by an Event Based Gateway. This will work as follows: once one of the elements (either the activity or event) is executed, then the others are no longer available.

To view more information and examples about the Event Based Gateway please review : http://wiki.bizagi.com/en/index.php?title=Event_Based_Gateway

Best regards,
Bizagi BPM Suite Support.